-
During a Jan. 14 Code Enforcement Board meeting, members voted to delay imposing fines on The Claridges Condominium.
-
Two code-enforcement cases involved the installation of cooling towers without the property permits or design review.
-
During the meeting, Claridge resident Mary Balcos criticized the condo's board and management for not informing residents about the code violations.
|
On Palm Beach's South End, Claridges Condominium has been caught up in two code-violation cases, after the cooling towers were installed at the property's two buildings without the town's approval. |
The issue first came before the code
board last April for the unpermitted cooling tower installed
at 3460 S. Ocean Blvd. At that meeting, the board chose to
levy a $150 administrative fee and give the condominium
until Aug. 21 to come into compliance.
During the Aug. 21 code board meeting, Claridges' attorney
James Gavigan said the condominium association had hired an
architect and was drafting documents required for a design
review and the permit-application process. That led the code
board to defer the fine-consideration case to its Dec. 18
meeting.
The case involving the other building, at
3456 S. Ocean Blvd., first surfaced at the board’s Oct. 16
meeting, during which code board members voted to defer the
hearing to its Dec. 18 meeting.
Throughout the process, Gavigan assured the board the condo
was applying for the proper permitting as quickly as
possible, but that it would take time to resolve.
That’s because the cooling towers must be reviewed by two
separate town bodies before the condo gets the greenlight.
The Architectural Commission’s would need to review the
designs of the cooling towers’ required screening, while the
town council would need to approve a variance to the town’s
zoning code, since the towers exceed Palm Beach’s height
threshold for rooftop mechanical equipment.
Adding to the delay are the elevation studies required for
the town’s application. Those were originally expected to be
completed before the board’s Dec. 18 meeting.
But when both cases returned before the board in December,
Gavigan said the condo was still working on completing its
application. Surveyors, he said at the time, had only
measured the elevation of the cooling towers, so the
required paperwork was still in the works.
Those surveys are now complete, and the project is coasting
through the application process, Gavigan said during the
Jan. 15 meeting. He told the board that the condo was on
track for the screening to be reviewed during the
Architectural Commission’s March meeting.
If the screening is approved by the design board, the
project's variance would head to the town council for review
in April.
Gavigan asked the board to delay the fine hearing for the
3460 S. Ocean Blvd building, because he said the condo was
working diligently to get the town’s approval.
“We can come back on a monthly basis, or bimonthly basis to
give you an update,” he said.
But he said any updates would only be about the application
process.
Although most board members appeared willing to extend the
deferment of fines, McGowan, who was absent from the
December hearing, questioned why the penalties should be
delayed. The condo, McGowan said, underwent nonemergency
work without doing the due diligence of checking what
requirements were needed to accommodate the installation of
the cooling towers.
“I'm confused as to why you didn’t go to the town with a
proposal to replace the aging equipment,” McGowan said.
Cabrera told the board he believed the contractor had filed
for the correct permits. Cabrera was notified of the
violations months later, he said.
But McGowan said he woud be more sympathetic if it were an
emergency project, such as if the previous cooling tower had
broken down.
“I’m not too excited about giving them a lot of
consideration on the fine program, but that’s just me,” he
said.
The situation has also drawn the ire of Balcos, who
criticized Cabrera for allowing the project to be completed
without the town’s approval.
According to Balcos, the code-violation cases have impeded
condo owners from selling their homes.
Residents, she said, had only learned about the violation
when they reached out to the town. Balcos even said she
wasn’t against the board imposing a daily running fine
against the condo.
“Maybe they’ll do something about who's running the
building, and make some changes,” she said.
But Board Member Chris Larmoyeux said it wasn’t in the code
board’s best interests to fine the condo. He noted that
representatives for Claridges had appeared at every code
board meeting and provided the board with updates each time.
He also emphasized that the condo is at the mercy of the
town’s schedule and has no means of seeking earlier meeting
dates for reviews by the Architectural Commission and the
town council.
"I think the idea of fining the condominium for something
that someone lied to them about (regarding the permit) just
doesn’t seem very fair and just,” he said
Vice Chair Scotch Peloso said that if the violations were
still evident in April, the board could impose daily running
fine with a retroactive starting date in January.
