The Florida law enacted in 2018 to
facilitate condominium owners’ installation of electric
vehicle charging stations within their limited common
element or exclusively designated parking spaces left a
number of important questions unanswered. A recent appellate
ruling has now provided insight on some of those questions
and on certain limitations that may impact an owner’s
installation of an EV charger in their parking area.
The ruling stems from a dispute over the installation of a
charger by the owners of a condo in the Station Square
Condominium in Clearwater, Florida. Franco Persechino and
Lina Teixeira sought to install the charger within their
unit’s assigned space in the parking garage, so they
submitted an application to the association.
The association initially denied their application and
developed its own form for future submissions. The unit
owners resubmitted their application using the new form but
they struck through certain questions, contending they were
outside of the statutory requirements for the installation
of an EV charger. The association again denied the
application, but the unit owners nevertheless proceeded with
the installation.
In response, the association sought and obtained a temporary
injunction from Pinellas County court, which found that the
owners made unauthorized material alterations to the
community’s common-element property. It concluded that the
installation used the association’s breaker box and
electricity in a manner that both limited their ability to
be used by all owners within the community and required the
duo to have access for future maintenance/repairs, which
would create a liability and safety concern for the
association.
The temporary injunction ordered the owners to stop using
the charging station, and it allowed the association to
disconnect it from the electrical supply. It also directed
the duo to submit an amended application with plans and
specifications that complied with the association’s new
application form, its rules and regulations, and Florida
law.
Feed Image In their subsequent appeal to the state’s Second
District Court of Appeal, the owners argued that the lower
court’s ruling violated the Florida law that protects the
right of condo owners to install an EV charger within their
designated parking area, and that prevents an association
from imposing requirements beyond those specifically listed
in the statute.
In its decision, the Second DCA rejected the owners’
argument and concluded that the five requirements listed in
the Florida Statutes are not the only conditions an
association may impose on owners seeking to install a
charger within their designated parking areas. The court
found that while Florida law prohibits associations from
outright prohibitions against owners installing chargers in
their designated parking areas, it does not prohibit them
from imposing reasonable requirements in addition to those
listed in the statute.
In fact, the court clarified that while the state law
exempts association-installed EV charging stations from
being considered a material alteration, a unit owner’s
installation of such chargers can constitute a material
alteration or substantial addition to the common elements in
certain circumstances. In situations where the facts support
that an owner’s installation is a material alteration, the
approval procedures for alterations to the common elements
prescribed under the community’s governing documents would
need to be followed.
If the documents do not specify a procedure, the court found
that 75% of the total voting interests of the association
must provide prior approval in accordance with state law. In
this case, the board president testified that the owners
attached the EV charging station to a common-element wall in
the parking garage, ran approximately 145 feet of electrical
lines to the association’s breaker box, made holes in the
box to gain access, and drilled holes in the garage wall and
ceiling to attach the conduit for the cables. Neither the
owners nor their electrician advised the association as to
the extent of the work performed, the materials used, how
the association’s breaker box was used or altered, nor the
location or depth of the holes drilled into the garage
ceiling to run the conduit. Also, while the owners attached
a meter to their charging station, the president indicated
that the association had no information about the meter or
what it was measuring.
The appellate panel found that the evidence presented
supported the lower court’s conclusion that the installation
qualified as a material alteration or substantial addition
that therefore required the prior approval of 75% of the
total voting interests of the association, in accordance
with its governing declaration. The court held that by
moving ahead with the installation before resolving the
application dispute and seeking approval of at least 75% of
thecommunity, the owners violated state law and the
condominium’s declaration. Accordingly, it affirmed that the
trial court did not err in granting the injunction.
A key takeaway from this ruling for Florida condominium
associations is that they may require more information,
plans, and approvals beyond the five items listed in the
state law, if appropriate and reasonable. They would be well
advised to work closely with qualified engineers and
attorneys to confirm what requirements and approvals are
reasonable or necessary for their community.
For unit owners, this case supports that the state’s law
preventing associations from barring owners from installing
personal EV chargers in their designated parking areas does
not mean owners have carte blanche authority to install them
in any manner of their choosing. Such installations can even
be considered material alterations or substantial additions
that may require approval from the membership, so it is
imperative for owners to first seek and obtain the
association’s input and consent.